Milestones are key dates used in the project schedule in which the project is evaluated, approved, and then paid for at every stage. A project may have a     single milestone, i.e., the final result or various interim steps along the way. Milestones are used as pre-scheduled check points to help with progress     and communication between the buyer and creator.

    Example 1: Mahogany Table for Rs. 10, 000

                                                                                                                                                                                                                                                                                                                                                                                   

                           

                    DELIVERY DATE                

           
               

                    AMOUNT                

           
               

                    Milestone 1                

           
               

                    7th March 2014                

           
               

                    2000/-                

           
               

                    Milestone 2                

           
               

                    10th March 2014                

           
               

                    2000/-                

           
               

                    Milestone 3                

           
               

                    15th March 2014                

           
               

                    2000/-                

           
               

                    Milestone 4                

           
               

                    18th March 2014                

           
               

                    2000/-                

           
               

                    Final Delivery of the product (within 9 days of shipment)                

           
               

                    27th March 2014                

           
               

                    2000/-                

           
               

                    Total                

           
                           

                    10,000/-                

           

    Example 2: Mahogany Table for Rs. 10, 000

                                                                                                                                                                                                                                                                                                                               

                           

                    DELIVERY DATE                

           
               

                    AMOUNT                

           
               

                    Milestone 1                

           
               

                    7th March 2014                

           
               

                    2000/-                

           
               

                    Milestone 2                

           
               

                    12th March 2014                

           
               

                    2000/-                

           
               

                    Milestone 3                

           
               

                    18th March 2014                

           
               

                    3000/-                

           
               

                    Final Delivery of the product (within 9 days of shipment)                

           
               

                    27th March 2014                

           
               

                    3000/-                

           
               

                    Total                

           
                           

                    10,000/-                

           

    Example 3: Mahogany Table for Rs. 10, 000

                                                                                                                                                                                                                                                                           

                           

                    DELIVERY DATE                

           
               

                    AMOUNT                

           
               

                    Milestone 1                

           
               

                    7th March 2014                

           
               

                    3000/-                

           
               

                    Milestone 2                

           
               

                    18th March 2014                

           
               

                    3000/-                

           
               

                    Final Delivery of the product (within 9 days of shipment)                

           
               

                    27th March 2014                

           
               

                    4000/-                

           
               

                    Total                

           
                           

                    10,000/-